letely remove oil stains, dust, release agents and other contaminants; rinse with high-pressure water if necessary.
- Flatness inspection: Use a 2m straightedge to check flatness; allowable deviation ≤ 4mm. Level and repair unqualified areas.
- Defect repairing: Repair cracks and holes with polymer mortar to ensure solid and stable base surface without loose parts.
- Interface treatment: Apply special interface agent on concrete and masonry bases to enhance bonding strength.
- Rock wool board: Adopt high-quality boards with uniform density, stable dimension and good hydrophobicity; thickness deviation shall not exceed ±2mm.
- Bonding material: Use special polymer bonding mortar only; prohibit arbitrary addition of cement or other materials to change the proportion.
- Auxiliary materials: Anchors shall be anti-corrosive, with length determined according to base type and insulation thickness.
- Proportion control: Mix strictly according to product instructions. Stir for no less than 5 minutes, stand for 3–5 minutes for maturation, then stir again before use.
- Application method: Combine strip bonding and spot-frame bonding. Bonding area ≥ 60% (≥70% for high-rise buildings).
- Thickness control: Mortar thickness shall be 5–8mm to guarantee stable bonding.
- Usage time: Finish use within 2 hours after mixing; no re-watering after initial set.
- Layout design: Optimize layout to reduce cutting. Adopt staggered joint laying; vertical joints shall stagger by 1/2 board length per row.
- Pasting sequence: Construct horizontally from bottom to top; finish corners first then large wall areas.
- Compaction process: Level with a 2m straightedge immediately after pasting; press evenly to allow slight mortar overflow at edges.
- Joint treatment: Joint gap ≤ 2mm, surface height difference ≤ 1.5mm.
- Anchoring time: Install anchors after mortar initial setting (normally after 24 hours).
- Anchor layout: 6–8 anchors per square meter; densify at edges and corners.
- Anchoring depth: ≥25mm for concrete base; ≥50mm for masonry base.
- Fixing sequence: Fix board center first, then four corners and edges.
- Door and window openings: Use integral boards; avoid joints at corner positions; add reinforced mesh around openings.
- Wall corners: Construct corner boards first to ensure verticality with staggered lap joints.
- Expansion joints: Reserve joints as designed, fill with elastic materials and conduct waterproof treatment.
- Temperature: Construction temperature 5–35℃; take thermal protection in winter.
- Humidity: Stop construction in rainy weather or on excessively wet bases; resume only after full drying.
- Wind condition: Stop construction under Grade 5 or above strong wind to prevent premature water loss of mortar.
- Preliminary inspection: Conduct percussion inspection section by section; mark hollow positions timely.
- Key inspection: Focus on corners, door and window openings and other critical parts.
- Record management: Keep complete inspection records for quality traceability.
- Visual inspection: Flat surface, tight joints and no visible hollowing.
- Percussion inspection: Hollow area ≤ 5cm×5cm is qualified.
- Pull-out test: Random sampling to ensure bonding strength meets design requirements.
1. Mark the hollowing range and formulate targeted repair schemes.
2. Grouting repair: Drill holes at hollow areas and inject special adhesive mortar.
3. Partial reconstruction: Remove and re-paste severely hollowed sections.
4. Extended curing time for repaired parts to ensure stability.
Systematic construction control can effectively prevent and eliminate hollowing defects in rock wool insulation projects. Strict implementation of standard procedures, precise material control and comprehensive on-site management ensure the overall quality, stability and durability of exterior wall thermal insulation systems.